Chapter 6: Q25P (page 138)
Question 25: (III) A 265-kg load is lifted 18.0 m vertically with an acceleration a = 0.160 g by a single cable. Determine (a) the tension in the cable; (b) the net work done on the load; (c) the work done by the cable on the load; (d) the work done by gravity on the load; (e) the final speed of the load assuming it started from rest.
Short Answer
- The tension in the cable is 3012.5 N.
- Net work done on the load is 7479.4 J.
- Work done by the cable on the load is 54,225 J.
- Work done by the gravity on the load is 46,746 J.
- The final speed of the load is \(7.51\;{\rm{m/s}}\).