In Exercises 5–8, use the following two control charts that result from testing batches of newly manufactured aircraft altimeters, with 100 in each batch. The original sample values are errors (in feet) obtained when the altimeters are tested in a pressure chamber that simulates an altitude of 6000 ft. The Federal Aviation Administration requires an error of no more than 40 ft at that altitude.

What is the value of\(\bar R\)? In general, how is a value of\(\bar R\)obtained?

Short Answer

Expert verified

The value of\(\bar R\)is equal to 67.0 feet.

The value of\(\bar R\)is obtained by taking the mean of the ranges of each of the subgroups, and its formula is given as follows:

\(\bar R = \frac{{{R_1} + {R_2} + ....{R_N}}}{N}\),

where

\({R_i}\)represents the ith sample range, and

N represents the total number of samples.

Step by step solution

01

Given information

The R chart is plotted for the measurement of errors (in feet) obtained when the aircraft altimetersare tested in a pressure chamber.

The individual sample size is equal to 100.

02

Step 2:Value of \(\bar R\)

By observing the R control chart, the value of\[\bar R\]is written on the left side of the chart adjacent to the central line.

Thus, the value of\[{\bf{\bar R}}\]is equal to 67.00 feet.

The general formula for computing the value of\[{\bf{\bar R}}\]is as follows:

\(\bar R = \frac{{{R_1} + {R_2} + .... + {R_N}}}{N}\),

where\({R_i}\)is the ith sample range, (i=1,2,…,N) and Nis the total number of samples.

First,obtain the range for each of the subgroupsand then take a sum of these ranges which is divided by the total number of samples.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Examine the following p-chart for defective calculator batteries and briefly describe the action that should be taken.a

Listed below are annual sunspot numbers paired with annual high values of the Dow Jones Industrial Average (DJIA). Sunspot numbers are measures of dark spots on the sun, and the DJIA is an index that measures the value of select stocks. The data are from recent and consecutive years. Use a 0.05 significance level to test for a linear correlation between values of the DJIA and sunspot numbers. Is the result surprising?

Sunspot

DJIA

45

10941

31

12464

46

14198

31

13279

50

10580

48

11625

56

12929

38

13589

65

16577

51

18054

Control Charts for p. In Exercises 5–12, use the given process data to construct a control chart for p. In each case, use the three out-of-control criteria listed near the beginning of this section and determine whether the process is within statistical control. If it is not, identify which of the three out-of-control criteria apply

Euro Coins Repeat Exercise 5, assuming that the size of each batch is 100 instead of 10,000. Compare the control chart to the one found for Exercise 5. Comment on the general quality of the manufacturing process described in Exercise 5 compared to the manufacturing process described in this exercise.

s Chart: In this section we described control charts for R and x based on ranges. Control charts for monitoring variation and center (mean) can also be based on standard deviations. An s chart for monitoring variation is constructed by plotting sample standard deviations with a centerline at s (the mean of the sample standard deviations) and control limits at B4s and B3s,where B4and B3 are found in Table 14-2 on page 660 in this section. Construct an s chart for the data of Table 14-1 on page 655. Compare the result to the R chart given in Example 3 “R Chart of Altimeter Errors.”

\(\bar x\)- Chart Based on Standard Deviations An x chart based on standard deviations (instead of ranges) is constructed by plotting sample means with a centerline at x and control limits at x + A3s and x - A3s, where A3 is found in Table 14-2 on page 660 and s is the mean of the sample standard deviations. Use the data in Table 14-1 on page 655 to construct an xchart based on standard deviations. Compare the result to the x chart based on sample ranges in Example 5 “x Chart of Altimeter Errors.”

See all solutions

Recommended explanations on Math Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free