Chapter 14: Q6BSC (page 654)
Control Charts for p. In Exercises 5–12, use the given process data to construct a control chart for p. In each case, use the three out-of-control criteria listed near the beginning of this section and determine whether the process is within statistical control. If it is not, identify which of the three out-of-control criteria apply
Euro Coins Repeat Exercise 5, assuming that the size of each batch is 100 instead of 10,000. Compare the control chart to the one found for Exercise 5. Comment on the general quality of the manufacturing process described in Exercise 5 compared to the manufacturing process described in this exercise.
Short Answer
The following p chart is constructed for the proportions of defective coins:
The process seems to be within statistical control since none of the three out-of-control criteria is visible from the chart.
The p chart corresponding to the sample size of 10,000 is nearly identical to the p chart shown above with a sample size of 100.
Because the two p charts have comparable outlooks, the manufacturing process quality for the two processes can also be considered to be the same.
Furthermore, whether the sample size is 100 or 10,000, the process produces good and reliable goods, and the manufacturer should continue with the current procedure.