Chapter 6: Problem 6
A fluoride tracer study is being conducted at a \(15.5\) MGD capacity water treatment plant. The contact time through the coagulation and flocculation process is \(2.45\) hours. If the sedimentation basin has a capacity of 500,000 gallons, what is the total detention time through the 3 processes?