Chapter 2: Problem 3
A construction crew will be installing 2,500 feet of 18 -inch diameter pipe. The width of the trench will be 40 inches and the depth 45 inches. After the pipe has been installed, how many cubic yards of dirt will be needed to backfill the trench? (Assume the trench will be backfilled up to 8 inches from the ground surface.)