Chapter 9: Q1MCQ (page 576)
For power-system fault studies, it is assumed that the system is operating under balanced steady-state conditions prior to the fault, and sequence networks are uncoupled before the fault occurs.
(a) True (b) False
Short Answer
The correct answer is (a) True.