Warning: foreach() argument must be of type array|object, bool given in /var/www/html/web/app/themes/studypress-core-theme/template-parts/header/mobile-offcanvas.php on line 20

(a) Draw the protective zones for the power system shown in Figure 10.45. Which circuit breakers should open for a fault at (a) P1, (b) P2, and (c) P3?

Short Answer

Expert verified

Answer

(a) The breakers B12a and B21a operates for the fault P1.

(b) The breaker should open when the fault occurred at P2are B21a, B21b, B24a, B24b and B23.

(c) The breaker should open when the fault occurred at P2are B21a, B21b, B24a, B24b, B32 and B23.

Step by step solution

01

Write the given data from the question.

Consider the system as,

02

Draw the protective zone of power system.

(a)

Consider the protective zone of the system as,

The breaker under the protection zone 3 are B12a and B21a.

When the fault occurred at P1, it lies under the protection zone 3 Therefore, the breaker B12a and B21a should operate under the fault at P1.

Hence breakers B12a and B21a operates for the fault P1.

03

Determine the breaker that operate under fault at P2.

(b)

When fault occurred at P2, it lies under the protective zone 7.

The breakers under the protection zone 7 are B21a, B21b, B24a, B24b and B23.

Therefore, the breaker should open when the fault occurred at P2are B21a, B21b, B24a, B24b and B23.

04

Determine the breaker that operate under fault at P3.

(c)

When the fault occurred at P3, it lies under the 2 two protective zones that are zone 6 and 7. The circuit breakers of zone 6 and 7 are highly sensitive against the fault under their zone.

The breakers under the protection zone 7 are B21a, B21b, B24a, B24b and B23.

The breakers under the protection zone 6 are B23 and B32.

Therefore, the breaker should open when the fault occurred at P2are B21a, B21b, B24a, B24b, B32 and B23.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

A simple system with circuit breaker-relay locations is shown in Figure 10.49. The six transmission-line circuit breakers are controlled by zone distance and directional relays, as shown in Figure 10.50. The three transmission lines have the same positive-sequence impedance of j0.1 per unit. The reaches for zones 1, 2 and 3 are 80, 120 and 250% , respectively. Consider only three-phase faults. (a) Find the settings Zrin per unit for all distance relays. (b) Convert the settings in V if the VTs are rated 133 kV : 115 V and the CTs are rated 400 : 5 A. (c) For a fault at location X, which is 10% down line TL31 from bus 3, discuss relay operations.

Figure 10.49

Figure 10.50

The primary conductor in Figure 10.2 is one phase of a three-phase transmission line operating at345โ€‰kV , 700โ€‰MVA,0.95 power factor lagging. The CT ratio is 1200:5, and the VT ratio is 3000:1. Determine the CT secondary currentI' and the VT secondary voltageV' . Assume zero CT error.

Line impedances for the power system shown in Figure 10.47 areZ12=Z23=3.0+j40.0, and Z24=6.0+j80.0. Reach for the zone 3B12 impedance a relay is set for 100% of line 1-2 plus 120% of line 2-4. (a) For a bolted three-phase fault at bus 4, show that the apparent primary impedance โ€œseenโ€ by the B12 relays is

Zapparent=Z12+Z24+(I32/I12)Z24

Where (I32/I12)is the line 2-3 to line 1-2 fault current ratio. (b) If |I32||I12|, does the B12 relay see the fault at bus 4? Note: This problem illustrates the โ€œinfeed effect.โ€ Fault currents from line 2-3 can cause the zone 3 B12relay to under reach. As such, remote backup of line 2-4 at B12is ineffective.

Figure 10.47

In addition to the costs of the relays, what other costs should be considered when upgrading relays?

What are the major reasons for failures of first generation numeric relay?

See all solutions

Recommended explanations on Computer Science Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free