Warning: foreach() argument must be of type array|object, bool given in /var/www/html/web/app/themes/studypress-core-theme/template-parts/header/mobile-offcanvas.php on line 20

What are the challenges associated with large penetrations of DERs in distribution systems?

Short Answer

Expert verified

Therefore, the location, type of technology and feeder response characteristics are the challenges associated with large penetrations of DERs in distribution systems.

Step by step solution

01

Distributed Energy Resources.

The Distributed Energy Resources are power generation resources and the small electrical device generally installed near the centre. The DERs reduce the fluctuation in the voltage and improve the voltage regulation for smooth transmission of power from generation end to user end.

02

Challenges associated with large penetrations of DERs.

The demand of the power from the customer end is very non traditional due to which the operation of transmission of power also changes accordingly. This creates a problem in installation of the DER location. The system requires the direct connectivity from the primary circuit for the distribution and technology due to this the technology of the DER also changes and the response of the DERs also change.

Hence,the location, type of technology and feeder response characteristics are the challenges associated with large penetrations of DERs in distribution systems.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question: Assume that a utilityโ€™s system consists of two feeders: feeder serving customers and feeder serving customers. Annual outage data during is given in Table 14.6 and 14.10 for these feeders. Calculate the SAIFI, SAIDI, CAIDI, and ASAI for the system, excluding the major event.

Do DER installations reduce distribution losses? If so, why?

What is the most common primary distribution voltage class in the United States?

Question: As shown in Figure 14.24, an urban distribution substation has one 30-MVA (FOA) and three 33.3 MVA (FOA), 138 kVD/12.5 kV Y transformers denoted TR1-TR4, which feed through circuit breakers to a ring bus. The transformers are older transformers designed for 55ยฐC temperature rise.

The ring bus contains eight bus-tie circuit breakers, two of which are normally open (NO), so as to separate the ring bus into two sections. TR1 and TR2 feed one section, and TR3 and TR4 feed the other section. Also, four capacitor banks, three banks rated at 6 Mvar and one at 9 Mvar, are connected to the ring bus. Twenty-four 12.5-kV underground primary feeders are served from the substation, 12 from each section. The utility that owns this substation has the following transformer summer loading criteria based on a percentage of nameplate rating:

a. 120% for normal summer loading.

b. 150% during a two-hour emergency.

c. 130% 30-day emergency loading.

Determine the following summer ratings of this substation: (a) the normal summer rating with all four transformers in service; (b) the allowable substation rating assuming the single-contingency loss of one transformer; and (c) the 30-day emergency rating under the single-contingency loss of one transformer. Assume that during a two-hour emergency, switching can be performed to reduce the total substation load by 10% and to approximately balance the loadings of the three transformers remaining in service. Assume a 5% reduction for unequal transformer loadings.

(a) How many Mvars of shunt capacitors are required to increase the power factor on a 10 MVA load from 0.85 to 0.9 lagging? (b) How manyMvars of shunt capacitors are required to increase the power factor on a 10 MVA load from 0.90 to 0.95 lagging? (c) Which requires more reactive power, improving a low power-factor load or a high power-factor load?

See all solutions

Recommended explanations on Computer Science Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free