One unit of Part C is used in item A and item B. Currently, we have 10 As, 20 Bs, and 100 Cs in inventory. We want to ship 60 As and 70 Bs. How many additional Cs do we need to purchase?

Short Answer

Expert verified

Answer

Zero units are required.

Step by step solution

01

Product tree

Item-A and B have a one-week lead time for assembly, while item C has a one-week lead time for procurement.

02

MRP schedule

Let's say the deadline for end-of-week items is in week three. Assemble an MRP scheduleas described in the following:

As indicated below, create a material requirements strategy using good amount ordering:

Available inventory = Initial inventory+ Scheduled receipts+ planned order receipts- Gross requirement

And

Net requirements = Gross requirements- previous weeks- Scheduled receipts

1. Each necessary order should have been issued one week before the neededweek, due to the one-week lead time.

2. Stockpile surplus merchandise and use the same elevated period as before.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.

Sign-up for free