How does synchronous manufacturing differ from MRP with respect to scheduling?
Short Answer
In terms of scheduling, MRP utilizes backward scheduling;on the other hand,synchronous manufacturing uses forward scheduling.
Chapter 4: Q13OQ (page 646)
How does synchronous manufacturing differ from MRP with respect to scheduling?
In terms of scheduling, MRP utilizes backward scheduling;on the other hand,synchronous manufacturing uses forward scheduling.
All the tools & learning materials you need for study success - in one app.
Get started for freeWhat would you suggest to improve the forecast described in question 10?
Question: When doing aggregate planning, these are the three general operations–related variables that can be varied.
Explain the need for the time fences in the master production schedule.
The planned order receipt and planned order release are offset by this amount of time.
None of the techniques for determining order quantity consider this important non-economic factor that could make the order quantity infeasible.
What do you think about this solution?
We value your feedback to improve our textbook solutions.