Chapter 1: Question 4-6OQ(c) (page 101)

Schedule the following activities using CPM:

Activity

Immediate Predecessor

Time (Weeks)

A

_

1

B

A

4

C

A

3

D

B

2

E

C,D

5

F

D

2

G

F

2

H

E,G

3

Short Answer

Expert verified

The project ending explains how the project purpose was met successfully. It encompasses the project's last step, which includes acceptance of the item, an analysis of the results, verification quality, as well as project closure settlement.

Step by step solution

01

Critical path completion project

In managing projects, a critical route is the largest series of operations that should be completed on schedule for the project to be finished. Any errors in crucial activities will cause the entire project to be delayed.

02

Critical path duration

Durationof critical path = 1+4+2+5+3=15

Finish timing of the project = 15 weeks.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.

Sign-up for free