Schedule the following activities using CPM:

Activity

Immediate Predecessor

Time (Weeks)

A

_

1

B

A

4

C

A

3

D

B

2

E

C,D

5

F

D

2

G

F

2

H

E,G

3

Short Answer

Expert verified

The critical path method (CPM) is a technique, tool, as well as algorithm for the planning phase including complicated, interconnected relationships.

Step by step solution

01

Critical path

The most significant tasks, as well as activities, are represented by the critical path, which is ordered into a logical order and also has a significant influence on the project’s conclusion schedule. These activities assist with work planning and resource distribution by identifying the work's maximum period.

02

Network Diagram

The network diagram is given below:

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.

Sign-up for free