The following activities are part of a project to be scheduled using CPM:

Activity

Immediate Predecessor

Time (Weeks)

A

_

6

B

A

3

C

A

7

D

C

2

E

B,D

4

F

D

3

G

E,F

7

Short Answer

Expert verified

The critical path method (CPM) is a strategy for identifying activities required for project finish as well as determining schedule flexibility.

Step by step solution

01

Draw the data given below

The followingdatais provided

Activity

Immediate Predecessor

Time (Weeks)

A

_

6

B

A

3

C

A

7

D

C

2

E

B,D

4

F

D

3

G

E,F

7

02

Draw a network diagram

The network diagram is shown below

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.

Sign-up for free