Chapter 1: Q18OQ (page 105)
Assume the network and data that follow:
Activity | Normal Time(Weeks) | Normal Cost | Crash Time(weeks) | Crash cost | Immediate Processors |
A | 2 | \(50 | 1 | \)70 | - |
B | 4 | 80 | 2 | 160 | A |
C | 8 | 70 | 4 | 110 | A |
D | 6 | 60 | 5 | 80 | A |
E | 7 | 100 | 6 | 130 | B |
F | 4 | 40 | 3 | 100 | D |
G | 5 | 100 | 4 | 150 | C,E,F |
a. Construct the network diagram.
b. Indicate the critical path when normal activity times are used.
c. Compute the minimum total direct cost for each project duration based on the cost associated with each activity. Consider the duration of 13, 14, 15, 16, 17, and 18 weeks.
d. If the indirect costs for each project duration are \(400 (18 weeks), \)350 (17 weeks), \(300 (16 weeks), \)250 (15 weeks), \(200 (14 weeks), and \)150 (13 weeks), what is the total project cost for each duration? Indicate the minimum total project cost duration.
Short Answer
The critical path is the longest path of the network diagram. It represents the minimum time required to complete the entire process.