The home office billing department of a chain of department stores prepares monthly inventory reports for use by the stores’ purchasing agents. Given the following information, use the critical path method to determine:

a. How long the total process will take.

b. Which jobs can be delayed without delaying the early start of any subsequent activity?

Job and Description

Immediate Predecessors

Time (Hours)

A

Start

_

0

B

Get computer printouts of customer purchases

A

10

C

Get stock records for the month

A

20

D

Reconcile purchase printouts and stock records

B, C

30

E

Total stock records by department

B, C

20

F

Determine reorder quantities for coming period

E

40

G

Prepare stock reports for purchasing agents

D,F

20

H

Finish

G

0

Short Answer

Expert verified

Department stores are huge retail facilities that provide a wide range of items in a singular location.

Step by step solution

01

The total long process will take

A billing department at a home office stores stock as well as provides a monthly stock record for the buying agent. Check out the following data on the direct predecessors as well as times of certain activities:

Create the project structure by utilizing the predecessor connection.

Determine the ES, EF, LS, as well as LF for slack using the formulas given below:

ES = newest EF for every direct predecessor…… (1)

EF = ES + task timing…… (2)

LF = early LS for every direct predecessor…… (3)

LS = LF + task timing…… (4)

Given below,

ES = Earliest beginning duration for a project task

EF = Earliest ending duration for a project task

LF = Newest ending duration for a project task

LS = Newest beginning duration for a project task

To determine the values of ES, LS, EF, LF, as well as slack as given below,

Inactivity A, C, E, F, G, as well as H have slack worth zero would be considered task critical. Therefore, the critical path is A, C, E, F, G, H as well as project timing

(0+20+20+40+20+0) = 100 Hours.

02

Jobs can be delayed without delaying the early start of any subsequent activity

In the image shown, activities B, as well as D, are not on the critical path. Their early start time can be forced back without affecting the beginning of any following events. As a result, activity B can be postponed for 10 hours as well as activity D can be postponed for 30 hours without affecting the project's finishing timeline.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Term that describes when multiple (usually similar) products can be produced in a facility less expensively than a single product.

The purpose of value analysis/value engineering is to…………………

In considering a capacity expansion we have two alternatives. The first alternative is expected to cost \(1,000,000 and has an expected profit of \)500,000 over the next three years. The second alternative has an expected cost of \(800,000 and expected a profit of \)450,000 over the next three years. Which alternative should we select, and what is the expected value of the expansion? Assume a 10 percent interest rate.

Match the following product types to the appropriate product development description.

Technology-push products A. Entail unusually large uncertainties about the technology or market. The development process takes steps to address those uncertainties.

Platform products B. A firm with a new proprietary technology seeks out a market where that technology can be applied.

Process-intensive products C. Uses a repeated prototyping cycle. Results from one cycle are used to modify priorities in the ensuing cycle.

High-risk products D. The production process has an impact on the product properties. Therefore, product design and process design cannot be separated.

Quick-build products E. Products are designed and built around a preexisting technological subsystem.

The following activities are part of a project to be scheduled using CPM:

Activity

Immediate Predecessor

Time (Weeks)

A

_

6

B

A

3

C

A

7

D

C

2

E

B,D

4

F

D

3

G

E,F

7

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free