Here is a CPM network with activity times in weeks:

How many weeks will the project take to complete?

Short Answer

Expert verified

The critical path technique is utilized to determine the most crucial activities as well as keep the project on track.

Step by step solution

01

Critical path

In managing projects, a critical path is the largest series of operations that should be completed on schedule for the whole project to be completed.

02

Project complete

The duration of the network's largest path, as well as the project, will require a maximum of 26 weeks to complete.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Study anywhere. Anytime. Across all devices.

Sign-up for free