Get started for freeA construction project is broken down into the following 10 activities:
Activity | Immediate Predecessor | Time (Weeks) |
1 | _ | 4 |
2 | 1 | 2 |
3 | 1 | 4 |
4 | 1 | 3 |
5 | 2,3 | 5 |
6 | 3 | 6 |
7 | 4 | 2 |
8 | 5 | 3 |
9 | 6,7 | 5 |
10 | 8,9 | 7 |
The home office billing department of a chain of department stores prepares monthly inventory reports for use by the stores’ purchasing agents. Given the following information, use the critical path method to determine:
a. How long the total process will take.
b. Which jobs can be delayed without delaying the early start of any subsequent activity?
Job and Description | Immediate Predecessors | Time (Hours) | |
A | Start | _ | 0 |
B | Get computer printouts of customer purchases | A | 10 |
C | Get stock records for the month | A | 20 |
D | Reconcile purchase printouts and stock records | B, C | 30 |
E | Total stock records by department | B, C | 20 |
F | Determine reorder quantities for coming period | E | 40 |
G | Prepare stock reports for purchasing agents | D,F | 20 |
H | Finish | G | 0 |
Term that describes when multiple (usually similar) products can be produced in a facility less expensively than a single product.
A chart that shows both the time and sequence for completing the activities in a project.
Here is a CPM network with activity times in weeks:
Suppose F could be shortened by two weeks and B by one week. How would this affect the completion date?