Chapter 2: Q.13-3C (page 343)
Question: Twelve additional samples of curetime data from the molding process were collected from an actual production run. The data from these new samples are shown below. Update your control charts and compare the results with the previous data. The X -and R-charts are drawn with the new data using the same control limits established before. Comment on what the new charts show.
Short Answer
Answer
The data shows the range and mean for 25 samples whereas also shows the values of the average of mean and range. Where the X bar is 30.40289 and the Range bar is 5.932155 (as shown in the table).