Chapter 18: Question 33E-c (page 1040)

(Recognition of Profit on Long-Term Contracts) During 2017, Nilsen Company started a construction job with a contract price of \(1,600,000. The job was completed in 2019. The following information is available.

2017 2018 2019

Costs incurred to date \)400,000 \(825,000 \)1,070,000

Estimated costs to complete 600,000 275,000 –0–

Billings to date 300,000 900,000 1,600,000

Collections to date 270,000 810,000 1,425,000

Instructions

(a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

(b) Prepare all necessary journal entries for 2018.

(c) Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

Short Answer

Expert verified

Gross profit for 2017, 2018, 2019 are $0, $0, $530,000 respectively.

Step by step solution

01

Meaning of Long-Term Contract

When you sign a long-term contract with someone else, you agree to work for them for a lengthy period of time. A long-term contract is also deemed complete since the parties will never need to change or renegotiate it as the future unfolds.

02

Gross profit for each year by the completed-contract method

Because the contract has not yet been finished, there will be no profit in 2017 and 2018. However, the profit in 2019 will be $530,000, which is the contract price less the cost incurred.

Grossprofitin2019=Contractprice-Costincurredin2019=$1,600,000-$1,070,000=$530,000

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

(Gross Profit on Uncompleted Contract) On April 1, 2017, Dougherty Inc. entered into a cost plus fixed fee contract to construct an electric generator for Altom Corporation. At the contract date, Dougherty estimated that it would take 2 years to complete the project at a cost of \(2,000,000. The fixed fee stipulated in the contract is \)450,000. Dougherty appropriately accounts for this contract under the percentage-of-completion method. During 2017, Dougherty incurred costs of \(800,000 related to the project. The estimated cost at December 31, 2017, to complete the contract is \)1,200,000. Altom was billed $600,000 under the contract.

Instructions

Prepare a schedule to compute the amount of gross profit to be recognized by Dougherty under the contract for the year ended December 31, 2017. Show supporting computations in good form.

Tyler Financial Services performs bookkeeping and tax-reporting services to startup companies in the Oconomowoc area. On January 1, 2017, Tyler entered into a 3-year service contract with Walleye Tech. Walleye promises to pay \(10,000 at the beginning of each year, which at contract inception is the standalone selling price for these services. At the end of the second year, the contract is modified and the fee for the third year of services is reduced to \)8,000. In addition, Walleye agrees to pay an additional $20,000 at the beginning of the third year to cover the contract for 3 additional years (i.e., 4 years remain after the modification). The extended contract services are similar to those provided in the first 2 years of the contract.

Instructions

(a) Prepare the journal entries for Tyler in 2017 and 2018 related to this service contract.

(b) Prepare the journal entries for Tyler in 2019 related to the modified service contract, assuming a prospective approach.

(c) Repeat the requirements for part (b), assuming Tyler and Walleye agree on a revised set of services (fewer bookkeeping services but more tax services) in the extended contract period and the modification results in a separate performance obligation.

What methods are used in practice to determine the extent of progress toward completion? Identify some “input measures” and some “output measures” that might be used to determine the extent of progress.

How do companies recognize revenue from a performance obligation over time?

(Contract Costs) Rex’s Reclaimers entered into a contract with Dan’s Demolition to manage the processing of recycled materials on Dan’s various demolition projects. Services for the 3-year contract include collecting, sorting, and transporting reclaimed materials to recycling centers or contractors who will reuse them. Rex’s incurs selling commission costs of \(2,000 to obtain the contract. Before performing the services, Rex’s also designs and builds receptacles and loading equipment that interfaces with Dan’s demolition equipment at a cost of \)27,000. These receptacles and equipment are retained by Rex’s and can be used for other projects. Dan’s promises to pay a fixed fee of \(12,000 per year, payable every 6 months for the services under the contract. Rex’s incurs the following costs: design services for the receptacles to interface with Dan’s equipment \)3,000, loading equipment controllers \(6,000, and special testing and OSHA inspection fees \)2,000 (some of Dan’s projects are on government property).

Instructions

(a) Determine the costs that should be capitalized as part of Rex’s Reclaimers revenue arrangement with Dan’s Demolition.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free