The Alexander Manufacturing Company in Rochester, Minnesota, assembles and tests electronic components used in smartphones. Consider the following data regarding component T24 (amounts are per unit):

Direct materials cost \( 81.00

Direct labor cost 21.00

Activity-based costs allocated ?

Total manufacturing product cost ?

The activities required to build the component follow:

Activity

Allocation Base

Cost Allocated to Each Unit

Start Station

Number of raw component chassis

3 X \)1.50 = \(4.50

Dip Insertion

Number of dip insertions

? X 0.50 = 14.50

Manual Insertion

Number of manual insertions

13 X 0.40 = ?

Wave solder

Number of components solders

3 X 1.50 = 4.50

Backload

Number of backload insertions

7 X ? = 2.80

Test

Number of testing hours

0.39 60.0 = ?

Defect analysis

Number of defect analysis hours

0.10 X ? = 4.00

Total activity-based costs

\) ?

Requirements

1. Complete the missing items for the two tables.

Short Answer

Expert verified

Activity based cost allocated: $58.9

Total manufacturing product cost: $160.9

No. of dip insertion: 29

Total Manual insertion cost: $5.2

Backload unit cost: $0.4

Total test cost: $23.4

Defect analysis unit cost: $40

Step by step solution

01

Step-by-Step-SolutionStep 1: Computation of missing figures for activity table

Numberofdipinsertion=TotalDipinsertioncostUnitCost=$14.50$0.50=29


Totalcostofmanualinsertion=No.ofmanualinsertion×UnitCost=13×$0.40=$5.2

Unitcostforbackload=TotalcostNo.ofbackloadinsertion=$2.87=$0.4

role="math" localid="1653284399133" Totaltestcost=No.oftestinghours×UnitCost=0.39×$60=$23.4

Unitcostfordefectanalysis=TotalcostNo.ofanalysishour=$40.1=$40

02

Computation of missing figure for component T24

Activitybasedcostallocated=Startstationcost+Dipinsertioncost+Manualinsertioncost+Wavesoldercost+Backloadcost+Teastcost+Defectanalysiscost=$4.5+$14.5+$5.2+$4.5+$2.8+$23.4+$4=$58.9


Totalmanufacturingproductcost=Activitybasedcostallocated+DirectMaterialcost+Directlaborcost=$58.9+$81+$21=$160.9

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

Harcourt Pharmaceuticals manufactures an over-the-counter allergy medication. The company sells both large commercial containers of 1,000 capsules to health care facilities and travel packs of 20 capsules to shops in airports, train stations, and hotels. The following information has been developed to determine if an activity-based costing system would be beneficial:

Activity Estimated Estimated Quantity

Indirect Cost Allocation Base of Allocation Base

Materials handling \( 96,000 Number of kilos 24,000 kilos

Packaging 210,000 Number of machine hours 3,000 hours

Quality assurance 114,000 Number of samples 1,900 samples

Total indirect costs \) 420,000

Other production information includes the following:

Commercial Containers Travel Packs

Units produced 2,800 containers 51,000 packs

Weight in kilos 9,800 5,100

Machine hours 1,960 510

Number of samples 560 765

Requirements

3. Use the predetermined overhead allocation rates to compute the activity-based costs per unit of the commercial containers and the travel packs. Round to two decimal places. (Hint: First compute the total activity-based costs allocated to each product line, and then compute the cost per unit.)

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

3. If Rennie desires an operating income of 30% of cost, how much should the company charge for the Brenton job?

Refer to Short Exercise S19-8. Spectrum Corp. desires a 25% target gross profit after covering all product costs. Considering the total product costs assigned to the Products C and D in Short Exercise S19-8, what would Spectrum have to charge the customer to achieve that gross profit? Round to two decimal places.

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

2. If Brenton paid $3,690 for the job, what is the operating income or loss?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free