Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

2. Prior to 2018, Eason used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

Short Answer

Expert verified

Predetermined overhead allocation rate: $30.93

Per unit indirect cost for Standard model: $155

Per unit indirect cost for Deluxe model: $186

Step by step solution

01

Step-by-Step-SolutionStep 1: Computation of single plantwide overhead allocation rate

Predeterminedoverheadallocationrate=TotalestimatedindirectcostTotaldirectlaborhour=$463,900(5+6)×500=$463,90015,000=$30.93

02

Per unit indirect cost for the standard model

Perunitcost=Predeterminedoverheadallocationrate×Directlaborhourperrimforstandardmodel=$30.93×5=$155

03

Per unit indirect cost for the deluxe model

Perunitcost=Predeterminedoverheadallocationrate×Directlaborhourperrimfordeluxemodel=$30.93×6=$186

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Brenton job?

What are quality improvement programs?

Question:Low Range produces fleece jackets. The company uses JIT costing for its JIT production system.

Low Range has two inventory accounts: Raw and In-Process Inventory and

Finished Goods Inventory. On March 1, 2018, the account balances were Raw and In-Process Inventory, \(9,000; Finished Goods Inventory, \)1,700.

The standard cost of a jacket is \(40, composed of \)12 direct materials plus \(28 conversion costs. Data for March’s activities follow:

Number of jackets completed 15,000

Number of jackets sold (on account, for \)50 each) 14,600

Direct materials purchased (on account) \( 177,500

Conversion costs incurred \) 521,000

Requirements

3. Use a T-account to determine the March 31, 2018, balance of Raw and In-Process Inventory.

Question:Treat Dog Collars uses activity-based costing. Treat’s system has the following features:

___________________________________________________________________

Activity Allocation BasePredetermined

Overhead Allocation Rate

Purchasing Number of purchase orders \( 60.00 per purchase order

Assembling Number of parts 0.36 per part

Packaging Number of finished collars 0.19 per collar

___________________________________________________________________

Each collar has three parts, direct materials cost is \)5.00 per collar, and direct laborcost is \(4.00 per collar. Suppose Animal Hut has asked for a bid on 30,000 dog collars.Treat will issue a total of 175 purchase orders if Animal Hut accepts Treat’s bid.

Requirements

1. Compute the total estimated cost Treat will incur to purchase the needed materialsand then assemble and package 30,000 dog collars. Also compute the cost percollar.

2. For bidding, Treat adds a 40% markup to total cost. What total price will the companybid for the entire Animal Hut order?

3. Suppose that instead of an ABC system, Treat has a traditional product costingsystem that allocates indirect costs at the rate of \)9.50 per direct labor hour. Thedog collar order will require 9,000 direct labor hours. What total price will Treat bidusing this system’s total cost?

4. Use your answers to Requirements 2 and 3 to explain how ABC can help Treatmake a better decision about the bid price it will offer Animal Hut.

Martin, Inc. manufactures bookcases and uses an activity-based costing system. Martin’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 230,000

Number of parts

\)1.50

Assembly

3,200,000

Number of assembling direct labor hours

16.00

Finishing

150,000

Number of finished units*

3.00

*Refers to the number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Martin produced two styles of bookcases in April: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

3,000

\(54,000

\)67,500

9,000

4,500

Unfinished bookcase

3,500

56,000

52,500

7,000

3,500

Requirements

2. Suppose that pre-manufacturing activities, such as product design, were assigned to the standard bookcases at \(5 each and to the unfinished bookcases at \)3 each. Similar analyses were conducted of post-manufacturing activities such as distribution, marketing, and customer service. The post-manufacturing costs were \(24 per standard bookcase and \)18 per unfinished bookcase. Compute the full product costs per unit.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free