Harris Systems specializes in servers for workgroup, e-commerce, and ERP applications. The company’s original job costing system has two direct cost categories: direct materials and direct labor. Overhead is allocated to jobs at the single rate of \(22 per direct labor hour.

A task force headed by Harris’s CFO recently designed an ABC system with four activities. The ABC system retains the current system’s two direct cost categories. Overhead costs are reflected in the four activities. Pertinent data follow:

___________________________________________________________________

Activity Allocation Base Predetermined Overhead

Allocation Rate____

Materials handling Number of parts \) 0.85

Machine setup Number of setups 500.00

Assembling Number of assembling hours 80.00

Shipping Number of shipments 1,500.00_______

Harris Systems has been awarded two new contracts, which will be produced as Job A and Job B. Budget data relating to the contracts follow:

____________________________________________________________

Job A Job B__

Number of parts 15,000 2,000

Number of setups 6 4

Number of assembling hours 1,500 200

Number of shipments 1 1

Total direct labor hours 8,000 600

Number of units produced 100 10

Direct materials cost \( 220,000 \) 30,000

Direct labor cost \( 160,000 \) 12,000__

Requirements

3. Which costing system more accurately assigns to jobs the costs of the resources consumed to produce them? Explain.

Short Answer

Expert verified

Activity-based costing more accurately allocate cost to a Job due to using the activity as the basis for allocating indirect cost.

Step by step solution

01

Step-by-Step-SolutionStep 1: Comparison of Budgeted cost under both the methods

Job A

Job B

Single Base Allocation Method

Total Budgeted Cost

$556,000

$393,200

Budgeted Cost per unit

$5,560

$39,320

Activity-Based Allocation Method

Total Budgeted Cost

$517,250

$63,200

Budgeted Cost per unit

$517.25

$6,320

02

Interpretation

Under the single base allocation method, the difference between the total budgeted costs for both the job has lower than in the activity-based allocation method. The reason for being is that the indirect cost has been computed based on the total labor hour in the first case.

The labor hour only is not the appropriate base for the allocation of direct cost. This is so because the overhead is incurred due to lots of manufacturing activities that are not directly related to production. The labor hour is the main activity for any production process but at the same time, all other indirect activities may not be involved in the production process as labor.

So if indirect cost is allocated or computed on the basis of labor hours it would cost more for the product or job that has very less amount of indirect activity.

In the given case, indirect activity is comparatively low for Job B. So when the indirect cost is allocated based on activity method it is apportioned fairly. But when labor hour is used for allocation then the Job having lower indirect activity is also allocated more cost due to labor hour activity.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

The following information is provided for Orbit Antenna Corp., which manufactures two products: Lo-Gain antennas and Hi-Gain antennas for use in remote areas.

Activity Cost Allocation Base

Setup \( 58,000 Number of setups

Machine maintenance 30,000 Number of machine hours

Total indirect manufacturing costs \) 88,000

Lo-Gain Hi-Gain Total

Direct labor hours 1,200 3,800 5,000

Number of setups 40 40 80

Number of machine hours 3,000 2,000 5,000

Orbit Antenna plans to produce 125 Lo-Gain antennas and 225 Hi-Gain antennas.

Requirements

2. Compute the ABC indirect manufacturing cost per unit for each product.

Martin, Inc. manufactures bookcases and uses an activity-based costing system. Martin’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 230,000

Number of parts

\)1.50

Assembly

3,200,000

Number of assembling direct labor hours

16.00

Finishing

150,000

Number of finished units*

3.00

*Refers to the number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Martin produced two styles of bookcases in April: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

3,000

\(54,000

\)67,500

9,000

4,500

Unfinished bookcase

3,500

56,000

52,500

7,000

3,500

Requirements

4. What price should Martin’s managers set for unfinished bookcases to earn a net profit of $19 per bookcase?

Question:Western, Inc. is a technology consulting firm focused on Web site development and integration of Internet business applications. The president of the company expectsto incur \(640,000 of indirect costs this year, and she expects her firm to work 4,000direct labor hours. Western’s systems consultants provide direct labor at a rate of \)280per hour. Clients are billed at 160% of direct labor cost. Last month, Western’s consultantsspent 170 hours on Halbert’s engagement.

Requirements

1. Compute Western’s predetermined overhead allocation rate per direct labor hour.

2. Compute the total cost assigned to the Halbert engagement.

3. Compute the operating income from the Halbert engagement.

List and define the four types of quality costs.

Franklin, Inc. uses activity-based costing to account for its chrome bumper manufacturing process. Company managers have identified four manufacturing activities:

materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for 2018 and their allocation bases are as follows:

Activity Total Budgeted Cost Allocation Base

Materials handling \( 12,000 Number of parts

Machine setup 3,100 Number of setups

Insertion of parts 42,000 Number of parts

Finishing 86,000 Finishing direct labor hours

Total \) 143,100

Franklin expects to produce 500 chrome bumpers during the year. The bumpers are expected to use 4,000 parts, require 10 setups, and consume 1,000 hours of finishing time.

Requirements

1. Compute the predetermined overhead allocation rate for each activity.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free