Harris Systems specializes in servers for workgroup, e-commerce, and ERP applications. The company’s original job costing system has two direct cost categories: direct materials and direct labor. Overhead is allocated to jobs at the single rate of \(22 per direct labor hour.

A task force headed by Harris’s CFO recently designed an ABC system with four activities. The ABC system retains the current system’s two direct cost categories. Overhead costs are reflected in the four activities. Pertinent data follow:

___________________________________________________________________

Activity Allocation Base Predetermined Overhead

Allocation Rate____

Materials handling Number of parts \) 0.85

Machine setup Number of setups 500.00

Assembling Number of assembling hours 80.00

Shipping Number of shipments 1,500.00_______

Harris Systems has been awarded two new contracts, which will be produced as Job A and Job B. Budget data relating to the contracts follow:

____________________________________________________________

Job A Job B__

Number of parts 15,000 2,000

Number of setups 6 4

Number of assembling hours 1,500 200

Number of shipments 1 1

Total direct labor hours 8,000 600

Number of units produced 100 10

Direct materials cost \( 220,000 \) 30,000

Direct labor cost \( 160,000 \) 12,000__

Requirements

1. Compute the budgeted product cost per unit for each job, using the original costing system (with two direct cost categories and a single overhead allocation rate).

Short Answer

Expert verified

Budgeted Product Cost per unit

For Product A: $5,560

For Product B: $39,320

Step by step solution

01

Step-by-Step-SolutionStep 1: Budgeted product cost for Job A

TotalIndirectCost=Predeterminedsingleoverheadallocationrate×No.ofdirectlaborhaour=$22×8,000=$176,000

TotalBudgetedCost=BudgetedDirectMaterialCost+BudgetedDirectLaborCost+BudgetedIndirectCost=$220,000+$160,000+$176,000=$556,000BudgetedProductCostperunit=TotalBudgetedCostTotalnumberofunitsproduced=$556,000100=$5,560

02

Budgeted product cost for Job B

TotalIndirectCost=Predeterminedsingleoverheadallocationrate×No.ofdirectlaborhaour=$22×600=$13,200

TotalBudgetedCost=BudgetedDirectMaterialCost+BudgetedDirectLaborCost+BudgetedIndirectCost=$220,000+$160,000+$13,200=$393,200

BudgetedProductCostperunit=TotalBudgetedCostTotalnumberofunitsproduced=$393,20010=$39,320

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

3. Compute the estimated ABC indirect manufacturing cost per unit of each model for 2018. Carry each cost to the nearest cent.

Loiselle manufactures high-quality speakers. Suppose Loiselle is considering spending the following amounts on a new quality program:

___________________________________________________________________

Additional 20 minutes of testing for each speaker \( 625,000

Negotiating and training suppliers to obtain higher-quality

materials and on-time delivery 430,000

Redesigning the speakers to make them easier to manufacture 1,250,000

Loiselle expects this quality program to save costs as follows:

__________________________________________________

Reduce warranty repair costs \) 275,000

Avoid inspection of raw materials 580,000

Avoid rework because of fewer defective units 825,000_

It also expects this program to avoid lost profits from the following:

___________________________________________________

Lost profits due to disappointed customers $ 920,000

Lost production time due to rework 278,000

Requirements

1. Classify each of these costs into one of the four categories of quality costs (prevention, appraisal, internal failure, or external failure).

2. Should Loiselle implement the quality program? Give your reasons.

Bubba and Danny are college friends planning a skiing trip to Killington before the New Year. They estimated the following for the trip:

Estimated Activity Allocation

Costs Allocation Base Bubba Danny

Food \( 400 Pounds of food eaten 24 26

Skiing 300 Number of lift tickets 2 0

Lodging 280 Number of nights 2 2

\) 980

Requirements

1. Bubba suggests that the costs be shared equally. Calculate the amount each person would pay.

The Oakman Company (see Short Exercise S19-1) has refined its allocation system by separating manufacturing overhead costs into two cost pools—one for each department. The estimated costs for the Mixing Department, \(510,000, will be allocated based on direct labor hours, and the estimated direct labor hours for the year are 170,000. The estimated costs for the Packaging Department, \)300,000, will be allocated based on machine hours, and the estimated machine hours for the year are 40,000. In October, the company incurred 38,000 direct labor hours in the Mixing Department and 10,000 machine hours in the Packaging Department.

Requirements

1. Compute the predetermined overhead allocation rates. Round to two decimal places.

Consider the following characteristics of either a JIT production system or a traditional production system. Indicate whether each is characteristic of a JIT production system or a traditional production system.

a. Products are produced in large batches.

b. Large stocks of finished goods protect against lost sales if customer demand ishigher than expected.

c. Suppliers make frequent deliveries of small quantities of raw materials.

d. Employees do a variety of jobs, including maintenance and setups as well as operating machines.

e. Machines are grouped into self-contained production cells or production lines.

f. Machines are grouped according to function. For example, all cutting machines are located in one area.

g. The final operation in the production sequence “pulls” parts from the preceding operation.

h. Each employee is responsible for inspecting his or her own work.

i. Management works with suppliers to ensure defect-free raw materials.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free