Activity-based costing requires four steps. List the four steps in the order they are performed.

Short Answer

Expert verified

The four steps in ABC are identifying activities, estimating their amount and allocation base, computing predetermined rate, and allocating overhead costs.

Step by step solution

01

Activity-based costing

Activity-based costing is a costing system in which the cost of activities is first determined. Then on the basis of such cost, the total cost of the product or services is determined.

Thus in the case of ABC, the overhead is segregated into different activities and then the activity costs are allocated based on an allocation base.

02

Four steps in activity-based costing

The listing of four steps in activity-based costing is as follows –

a) Identify activities and estimate their total indirect costs

b) Identifying the allocation base and estimating the total quantity for each allocation base

c) To compute a predetermined overhead allocation rate for each activity

d) Allocating indirect costs to cost objects

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question:Refer to Exercises E19-24 and E19-25. Suppose Western’s direct labor rate was $280 per hour. The Halbert engagement used the following resources last month:

Allocation Base Halbert

Direct labor hours 170

Pages 310

Applications used 80

Requirements

1. Compute the cost assigned to the Halbert engagement, using the ABC system.

2. Compute the operating income or loss from the Halbert engagement, using theABC system.

What are quality improvement programs?

Refer to Exercises E19-20 and E19-21. Controller Michael Bender is surprised by the increase in cost of the deluxe model under ABC. Market research shows that for the deluxe rim to provide a reasonable profit, Eason will have to meet a target manufacturing cost of \(625.00 per rim. A value engineering study by Eason’s employees suggests that modifications to the finishing process could cut finishing cost from \)90.00 to \(60.00 per hour and reduce the finishing direct labor hours per deluxe rim from 5.50 hours to 5.0 hours. Direct materials would remain unchanged at \)48.00 per rim, as would direct labor at $52.00 per rim. The materials handling, machine setup, and insertion of parts activity costs also would remain the same.

Would implementing the value engineering recommendation enable Eason to achieve its target cost for the deluxe rim?

“Prevention is much cheaper than external failure.” Do you agree with this statement? Why or why not?

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free