The Oakman Company (see Short Exercise S19-1) has refined its allocation system by separating manufacturing overhead costs into two cost pools—one for each department. The estimated costs for the Mixing Department, \(510,000, will be allocated based on direct labor hours, and the estimated direct labor hours for the year are 170,000. The estimated costs for the Packaging Department, \)300,000, will be allocated based on machine hours, and the estimated machine hours for the year are 40,000. In October, the company incurred 38,000 direct labor hours in the Mixing Department and 10,000 machine hours in the Packaging Department.

Requirements

2. Determine the total amount of overhead allocated in October.

Short Answer

Expert verified

Total overhead in October is $189,000.

Step by step solution

01

Overhead cost or mixing department

overhaedcostinoctober=predeterminedoverheadallocationrate×directlaborhourinoctober=$3×38,000=$114,000

02

Overhead cost or packaging department

overhaedcostinoctober=predeterminedoverheadallocationrate×directmachinehourinoctober=$7.5×10,000=$75,000

03

Total Overhead allocated in October

totaloverhaedcostinoctober=overheadallocationformixingdepartment+overheadallocationforpackingdepartment=$114,000+75,000=$189,000

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

2. Prior to 2018, Eason used a single plantwide overhead allocation rate system with direct labor hours as the allocation base. Compute the predetermined overhead allocation rate based on direct labor hours for 2018. Use this rate to determine the estimated indirect manufacturing cost per wheel rim for each model, to the nearest cent.

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Brenton job?

Turbo Champs Corp. uses activity-based costing to account for its motorcycle manufacturing process. Company managers have identified three supporting manufacturing activities: inspection, machine setup, and machine maintenance. The budgeted activity costs for 2018 and their allocation bases are as follows:

Activity Total Budgeted Cost Allocation Base

Inspections \( 5,700 Number of inspections

Machine setup 22,000 Number of setups

Machine maintenance 6,000 Finishing of machine hours

Total \) 33,700

Turbo Champs expects to produce 20 custom-built motorcycles for the year. The motorcycles are expected to require 100 inspections, 40 setups, and 100 machine hours.

Requirements

2. Compute the expected indirect manufacturing cost of each motorcycle.

Question:Stella, Inc. is using a costs-of-quality approach to evaluate design engineering efforts for a new skateboard. Stella’s senior managers expect the engineering work to reduce appraisal, internal failure, and external failure activities. The predicted reductions in activities over the two-year life of the skateboards follow. Also shown are the predetermined overhead allocation rates for each activity.

Activity Predicted Predetermined

Reduction in Overhead Allocation

Activity Units Rate per Unit

Inspection of incoming raw materials 390 $ 44

Inspection of finished goods 390 19

Number of defective units discovered in-house 1,200 50

Number of defective units discovered by customers 325 72

Lost profits due to dissatisfied customers 75 102

Requirements

3. What major difficulty would Stella’s managers have in implementing this costs-of-quality approach? What alternative approach could they use to measure quality improvement?

Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscar’s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

2. Suppose that pre-manufacturing activities, such as product design, were assigned to the standard bookcases at \(5 each and to the unfinished bookcases at \)3 each. Similar analyses were conducted of post-manufacturing activities such as distribution, marketing, and customer service. The post-manufacturing costs were \(20 per standard bookcase and \)18 per unfinished bookcase. Compute the full product costs per unit.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free