Turbo Champs Corp. uses activity-based costing to account for its motorcycle manufacturing process. Company managers have identified three supporting manufacturing activities: inspection, machine setup, and machine maintenance. The budgeted activity costs for 2018 and their allocation bases are as follows:

Activity Total Budgeted Cost Allocation Base

Inspections \( 5,700 Number of inspections

Machine setup 22,000 Number of setups

Machine maintenance 6,000 Finishing of machine hours

Total \) 33,700

Turbo Champs expects to produce 20 custom-built motorcycles for the year. The motorcycles are expected to require 100 inspections, 40 setups, and 100 machine hours.

Requirements

1. Compute the predetermined overhead allocation rate for each activity.

Short Answer

Expert verified

Predetermined overhead allocation rate

Inspection: $57

Machine setup: $55

Machine maintenance: $60

Step by step solution

01

Inspection

PredeterminedOverheadAllocationrate=InspectionCostNumberofinspections=$5,700100=$57

02

Machine setup

PredeterminedOverheadAllocationrate=MachinesetupCostNumberofsetups=$22,0040=$55

03

Machine maintenance

PredeterminedOverheadAllocationrate=MachinemaintenanceCostNumberoffinfishingmachinehour=$6,000100=$60

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Harris Systems specializes in servers for workgroup, e-commerce, and ERP applications. The companyโ€™s original job costing system has two direct cost categories: direct materials and direct labor. Overhead is allocated to jobs at the single rate of \(22 per direct labor hour.

A task force headed by Harrisโ€™s CFO recently designed an ABC system with four activities. The ABC system retains the current systemโ€™s two direct cost categories. Overhead costs are reflected in the four activities. Pertinent data follow:

___________________________________________________________________

Activity Allocation Base Predetermined Overhead

Allocation Rate____

Materials handling Number of parts \) 0.85

Machine setup Number of setups 500.00

Assembling Number of assembling hours 80.00

Shipping Number of shipments 1,500.00_______

Harris Systems has been awarded two new contracts, which will be produced as Job A and Job B. Budget data relating to the contracts follow:

____________________________________________________________

Job A Job B__

Number of parts 15,000 2,000

Number of setups 6 4

Number of assembling hours 1,500 200

Number of shipments 1 1

Total direct labor hours 8,000 600

Number of units produced 100 10

Direct materials cost \( 220,000 \) 30,000

Direct labor cost \( 160,000 \) 12,000__

Requirements

1. Compute the budgeted product cost per unit for each job, using the original costing system (with two direct cost categories and a single overhead allocation rate).

Koehler makes handheld calculators in two models: basic and professional. Koehler estimated $721,000 of manufacturing overhead and 515,000 machine hours for the year. The basic model actually consumed 230,000 machine hours, and the professional model consumed 285,000 machine hours.

Compute the predetermined overhead allocation rate using machine hours (MHr) as the allocation base. How much overhead is allocated to the basic model? To the professional model?

Which accounts are adjusted for the underallocated or overallocated overhead in JIT costing?

Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscarโ€™s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

3. Which product costs are reported in the external financial statements? Which costs are used for management decision-making? Explain the difference.

Question:Oscar, Inc. manufactures bookcases and uses an activity-based costing system. Oscarโ€™s activity areas and related data follow:

Activity

Budgeted Cost of Activity

Allocation Base

Predetermined Overhead Allocation Rate

Materials handling

\( 240,000

Number of parts

\)1.00

Assembly

3,500,000

Number of assembling direct labor hours

17.00

Finishing

190,000

Number of finished units*

4.50

*Refers to number of units receiving the finishing activity, not the number of units transferred to Finished Goods Inventory

Oscar produced two styles of bookcases in October: the standard bookcase and an unfinished bookcase, which has fewer parts and requires no finishing. The totals for quantities, direct materials costs, and other data follow:

Product

Total Units Produced

Total Direct materials Costs

Total Direct Labor Costs

Total Number of Parts

Total Assembling Direct Labor Hours

Standard bookcase

7,000

\(91,000

\)105,000

28,000

10,500

Unfinished bookcase

7,500

82,500

75,000

22,500

7,500

Requirements

4. What price should Oscarโ€™s managers set for unfinished bookcases to earn a net profit of $19 per bookcase?

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free