Turbo Champs Corp. uses activity-based costing to account for its motorcycle manufacturing process. Company managers have identified three supporting manufacturing activities: inspection, machine setup, and machine maintenance. The budgeted activity costs for 2018 and their allocation bases are as follows:

Activity Total Budgeted Cost Allocation Base

Inspections \( 5,700 Number of inspections

Machine setup 22,000 Number of setups

Machine maintenance 6,000 Finishing of machine hours

Total \) 33,700

Turbo Champs expects to produce 20 custom-built motorcycles for the year. The motorcycles are expected to require 100 inspections, 40 setups, and 100 machine hours.

Requirements

2. Compute the expected indirect manufacturing cost of each motorcycle.

Short Answer

Expert verified

Answer

Indirect cost per motorcycle: $172

Step by step solution

01

Indirect Manufacturing cost

Indirect manufacturing costs are the costs that are not visible in the production process but help the production process to run efficiently. These costs cannot be directly attributed to each product or service but can be allocated based on some allocation base.

02

Calculation of indirect manufacturing cost per bumper

The predetermined overhead allocation rate computed in the earlier part is as follow: –

Inspection: $57

Machine setup: $55

Machine maintenance: $60

The indirect cost for each motorcycle would be the sum of all the allocation rate.


Indirectcostperbumper=Inspectionrate+Machinesetuprate+Machinemaintenance=$57+$55+$60=$172

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Question:Blanchette Plant Service completed a special landscaping job for Kerry Company. Blanchette uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Kerry job included \(750 in plants; \)1,300 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Kerry job?

The Oakman Company (see Short Exercise S19-1) has refined its allocation system by separating manufacturing overhead costs into two cost pools—one for each department. The estimated costs for the Mixing Department, \(510,000, will be allocated based on direct labor hours, and the estimated direct labor hours for the year are 170,000. The estimated costs for the Packaging Department, \)300,000, will be allocated based on machine hours, and the estimated machine hours for the year are 40,000. In October, the company incurred 38,000 direct labor hours in the Mixing Department and 10,000 machine hours in the Packaging Department.

Requirements

1. Compute the predetermined overhead allocation rates. Round to two decimal places.

Eason Company manufactures wheel rims. The controller expects the following ABC allocation rates for 2018:

Activity Allocation Base Predetermined Overhead

Allocation Rate

Materials handling Number of parts $ 4.00 per part

Machine setup Number of setups 400.00 per setup

Insertion of parts Number of parts 26.00 per part

Finishing Number of finishing hours 90.00 per hour

Eason produces two wheel rim models: standard and deluxe. Expected data for 2018 are as follows:

Standard Deluxe

Parts per rim 4.0 7.0

Setups per 500 rims 18.0 18.0

Finishing hours per rim 1.0 5.5

Total direct hours per rim 5.0 6.0

The company expects to produce 500 units of each model during the year.

Requirements

3. Compute the estimated ABC indirect manufacturing cost per unit of each model for 2018. Carry each cost to the nearest cent.

Question:Stella, Inc. is using a costs-of-quality approach to evaluate design engineering efforts for a new skateboard. Stella’s senior managers expect the engineering work to reduce appraisal, internal failure, and external failure activities. The predicted reductions in activities over the two-year life of the skateboards follow. Also shown are the predetermined overhead allocation rates for each activity.

Activity Predicted Predetermined

Reduction in Overhead Allocation

Activity Units Rate per Unit

Inspection of incoming raw materials 390 \( 44

Inspection of finished goods 390 19

Number of defective units discovered in-house 1,200 50

Number of defective units discovered by customers 325 72

Lost profits due to dissatisfied customers 75 102

Requirements

2. Stella spent \)103,000 on design engineering for the new skateboard. What is the net benefit of this “preventive” quality activity?

The Alright Manufacturing Company in Rochester, Minnesota, assembles and tests electronic components used in smartphones. Consider the following data regarding component T24 (amounts are per unit):

Direct materials cost \( 80.00

Direct labor cost 20.00

Activity-based costs allocated ?

Total manufacturing product cost ?

The activities required to build the component follow:

Activity Allocation Base Cost Allocated to

Each Unit

Start station Number of raw component chassis 4 * \) 1.50 = \( 6.00

Dip insertion Number of dip insertions ? * 0.30 = 9.60

Manual insertion Number of manual insertions 10 * 0.50 = ?

Wave solder Number of components soldered 4 * 1.90 = 7.60

Backload Number of backload insertions 7 * ? = 4.20

Test Number of testing hours 0.43 * 90.00 = ?

Defect analysis Number of defect analysis hours 0.15 * ?= 12.00

Total activity-based costs \) ?

Requirements

1. Complete the missing items for the two tables.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free