Franklin, Inc. uses activity-based costing to account for its chrome bumper manufacturing process. Company managers have identified four manufacturing activities:

materials handling, machine setup, insertion of parts, and finishing. The budgeted activity costs for 2018 and their allocation bases are as follows:

Activity Total Budgeted Cost Allocation Base

Materials handling \( 12,000 Number of parts

Machine setup 3,100 Number of setups

Insertion of parts 42,000 Number of parts

Finishing 86,000 Finishing direct labor hours

Total \) 143,100

Franklin expects to produce 500 chrome bumpers during the year. The bumpers are expected to use 4,000 parts, require 10 setups, and consume 1,000 hours of finishing time.

Requirements

2. Compute the expected indirect manufacturing cost of each bumper.

Short Answer

Expert verified

Answer

Indirect cost per bumper: $409.5

Step by step solution

01

Indirect Manufacturing cost

Indirect manufacturing costs are the costs that are not visible in the production process but help the production process to run efficiently. These costs cannot be directly attributed to each product or service but can be allocated based on some allocation base.

02

Calculation of indirect manufacturing cost per bumper

Predetermined overhead allocation rate computed in the earlier part are as follow –

Material handling: $3

Machine setup: $310

Insertion of parts: $10.5

Finishing: $86

The indirect cost for each bumper would be the sum of all the allocation rate

Indirectcostperbumper=Materialhandlingrate+Machinesetuprate+Insertionofpartsrate+Finishingrate=$3+$310+$10.5+$86=$409.5

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

1. What is the total cost of the Brenton job?

The Alexander Manufacturing Company in Rochester, Minnesota, assembles and tests electronic components used in smartphones. Consider the following data regarding component T24 (amounts are per unit):

Direct materials cost \( 81.00

Direct labor cost 21.00

Activity-based costs allocated ?

Total manufacturing product cost ?

The activities required to build the component follow:

Activity

Allocation Base

Cost Allocated to Each Unit

Start Station

Number of raw component chassis

3 X \)1.50 = \(4.50

Dip Insertion

Number of dip insertions

? X 0.50 = 14.50

Manual Insertion

Number of manual insertions

13 X 0.40 = ?

Wave solder

Number of components solders

3 X 1.50 = 4.50

Backload

Number of backload insertions

7 X ? = 2.80

Test

Number of testing hours

0.39 60.0 = ?

Defect analysis

Number of defect analysis hours

0.10 X ? = 4.00

Total activity-based costs

\) ?

Requirements

1. Complete the missing items for the two tables.

Bubba and Danny are college friends planning a skiing trip to Killington before the new year. They estimated the following for the trip:

Estimated Activity Allocation

Costs Allocation Base Bubba Danny

Food \( 400 Pounds of food eaten 24 26

Skiing 300 Number of lift tickets 2 0

Lodging 280 Number of nights 2 2

\) 980

Requirements

2. Danny does not like the idea of sharing the costs equally because he plans to stay in the room rather than ski. Danny suggests that each type of cost be allocated to each person based on the above-listed allocation bases. Using the activity allocation for each person, calculate the amount that each person would pay based on his own consumption of the activity.

Rennie Plant Service completed a special landscaping job for Brenton Company. rennie uses ABC and has the following predetermined overhead allocation rates:

Activity Predetermined

Allocation Base Overhead Allocation Rate

Designing Number of designs \( 290 per design

Planting Number of plants \) 20 per plant

The Rennie job included \(1,500 in plants; \)800 in direct labor; one design; and 30 plants.

Requirements

2. If Brenton paid $3,690 for the job, what is the operating income or loss?

Question:Gateway produces electronic calculators. Suppose Gateway’s standard cost per calculator is \(25 for direct materials and \)68 for conversion costs. The following data applyto August activities:

Direct materials purchased (on account) \( 8,300

Conversion costs incurred 20,500

Number of calculators produced 300 calculators

Number of calculators sold (on account, at \)105 each) 295 calculators

Requirements

1. Prepare summary journal entries for August using JIT costing, including the entryto adjust the Conversion Costs account.

2. The beginning balance of Finished Goods Inventory was $1,300. Use a T-accountto find the ending balance of Finished Goods Inventory.

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free