Google monitors its fixed overhead. In an analysis of fixed overhead cost variances, what is the volume variance?

Short Answer

Expert verified

The differences in the actual cost obtained from the actual production is termed overhead volume variance.

Step by step solution

01

Meaning of Fixed Cost

In accounting, the term fixed cost denotes the expenses that are independent or not dependent on production level. Such costs remain the same for all production levels and are not directly associated with the manufacturing process.

02

Volume variance in fixed overhead cost variance

The expenses incurred by a business entity for a definite production level are termed overhead costs. It includes variable and fixed expenses that facilitate drafting a flexible budget. The actual fixed overhead cost differences obtained from the actual product produced during a particular period state the overhead volume variance.

Unlock Step-by-Step Solutions & Ace Your Exams!

  • Full Textbook Solutions

    Get detailed explanations and key concepts

  • Unlimited Al creation

    Al flashcards, explanations, exams and more...

  • Ads-free access

    To over 500 millions flashcards

  • Money-back guarantee

    We refund you if you fail your exam.

Over 30 million students worldwide already upgrade their learning with Vaia!

One App. One Place for Learning.

All the tools & learning materials you need for study success - in one app.

Get started for free

Most popular questions from this chapter

City Companyโ€™s fixed budget performance report for July follows. The \(647,500 budgeted total expenses include \)487,500 variable expenses and \(160,000 fixed expenses. Actual expenses include \)158,000 fixed expenses. Prepare a flexible budget performance report that shows any variances between budgeted results and actual results. List fixed and variable expenses separately.

Fixed Budget Actual Results Variances

Sales (in units) 7,500 7,200

Sales (in dollars) \(750,000 \)737,000 \(13,000 U

Total expenses 647,500 641,000 6,500 F

Income from operations \)102,500 \(96,000 \)6,500 U

Refer to information in QS 21-14. Compute the overhead volume variance for November and classify it as favorable or unfavorable.

Presented below are terms preceded by letters a through j and a list of definitions 1 through 10. Enter the letter of the term with the definition, using the space preceding the definition.

  1. Fixed budget

1. The difference between actual and budgeted sales or cost caused by the difference between the actual price per unit and the budgeted price per unit.

  1. Standard costs

2. A planning budget based on a single predicted amount of sales or production volume; unsuitable for evaluations if the actual volume differs from the predicted volume.

  1. Price variance

3. Preset costs for delivering a product, component, or service under normal conditions.

  1. Quantity variance

4. A process of examining the differences between actual and budgeted sales or costs and describing them in terms of the amounts that resulted from price and quantity differences.

  1. Volume variance

5. The difference between the total budgeted overhead cost and the overhead cost that was allocated to products using the predetermined fixed overhead rate.

  1. Controllable variance

6. A budget prepared based on predicted amounts of revenues and expenses corresponding to the actual level of output.

  1. Cost variance

7. The difference between actual and budgeted cost caused by the difference between the actual quantity and the budgeted quantity.

  1. Flexible budget

8. The combination of both overhead spending variances (variable and fixed) and the variable overhead efficiency variance.

  1. Variance analysis

9. A management process to focus on significant variances and give less attention to areas where performance is close to the standard.

  1. Management by exception

10. The difference between actual cost and standard cost, made up of a price variance and a quantity variance.

After evaluating Null Companyโ€™s manufacturing process, management decides to establish standards of 3 hours of direct labor per unit of product and \(15 per hour for the labor rate. During October, the company uses 16,250 hours of direct labor at a \)247,000 total cost to produce 5,600 units of product. In November, the company uses 22,000 hours of direct labor at a $335,500 total cost to produce 6,000 units of product.

1. Compute the direct labor rate variance, the direct labor efficiency variance, and the total direct labor cost variance for each of these two months. Classify each variance as favorable or unfavorable.

2. Interpret the October direct labor variances.

Business Solutionsโ€™s second-quarter 2018 fixed budget performance report for its computer furniture operations follows. The \(156,000 budgeted expenses include \)108,000 in variable expenses for desks and \(18,000 in variable expenses for chairs, as well as \)30,000 fixed expenses. The actual expenses include \(31,000 fixed expenses. Prepare a flexible budget performance report that shows any variances between budgeted results and actual results. List fixed and variable expenses separately.


Fixed Budget

Actual Results

Variances

Desk sales (in units)

144

150


Chair sales (in units)

72

80


Desk sales

\)180,000

\(186,000

\)6,000 F

Chair sales

36,000

41,200

5,200 F

Total expenses

156,000

163,880

7,880 U

Income from operations

\(60,000

\)63,320

$3,320 F

See all solutions

Recommended explanations on Business Studies Textbooks

View all explanations

What do you think about this solution?

We value your feedback to improve our textbook solutions.

Study anywhere. Anytime. Across all devices.

Sign-up for free